Nine Network Australia - Stage 2

'Project Refresh'

$10 million ‘Project Refresh’, constructed over 18 months in five stages to minimise disruption to 24-hour-7-day operations, presented a significant logistical challenge.

Brewster Murray was responsible as design team, project manager and architects for the entire project, completing the overall program of works on time and on budget.

The Stage 2 fitout addressed NNA’s needs to accommodate the news team on one floor and prepare the outdated second floor for expansion of the business units. All this, whilst providing a contemporary, state-of-the-art fitout suitable as a backdrop to News television broadcasts and bringing NNA into the twenty-first century.

Facilities provided encompass News Room, 'Gateway’, ‘Video Graphics’, Edit Suites, Offices, Meeting Rooms, Break-out Areas; storage and toilets.